Capital Projects

The Engineering Department has been implementing projects from the 2008-2012 Capital Improvement Program, in the area of public infrastructure (roads, utilities and drainage). The ever-increasing challenges of a thriving and growing community have necessitated improvements in all categories.
  1. ROADS
  2. Utilities
  3. Facilities
  4. Maps & Links
Right Hand Turn Lane

2015 Intersection Improvements


(Right Turn Lanes) 
Project Manager: Kevin Bates

Start: Estimated late Spring 2018
  • Eastbound McDermott at US 75
  • Westbound McDermott at US 75
  • Northbound Greenville at Exchange
Allen Drive / US 75 Interchange

Allen Drive / US 75 Interchange Improvements

Project Manager: Kevin Bates

Start: TBD



  •  Project is in design phase to investigate options for improvements.
Lanes.png

Alma Drive Improvements


(Hedgcoxe to SH 121) 
Project Manager: Kevin Bates

Start: TBD
Bethany Intersections Improvements Bethany Intersections Improvements
(Watters and Watters Creek) 
Project Contact: Lindy Higginbotham

Begin: Late Spring 2018

  • Currently in design
CBD Asphalt Rehab

CBD Asphalt Rehabilitation


Project Contact: Lindy Higginbotham

Completion: Spring 2018
  • Project will begin after gas line relocations
ENG_1378.jpg

FM 1378 / Country Club Road

 
(North of Farmstead Road, Fairview, to south of White Rock Bridge) 

This project has been suspended due to lack of consensus through partner cities of Fairview, Lucas, and Allen. 
  • TxDOT project
  • No formal schedule for construction until construction funding can be established
FM 2551 Angel Parkway

FM 2551 / Angel Parkway 


(Main to southern City Limits)
Project Contact: Chris Flanigan
  • Design being managed by Collin County to widen to 6 lanes
  • Construction not anticipated in 2020
  • No formal schedule for construction until construction funding can be established
Ridgemont Ridgemont Drive
(Greenville to US 75) 
Project Contact: Lindy Higginbotham

Completion: December 2017
  • Construction by developer
  • Road between Greenville and Railroad tracks anticipated to be closed until December 31, 2017
Ridgeview Phase 2

Ridgeview Drive, Phase 2


(Watters to Chelsea)
Project Manager: Lindy Higginbotham

Completion: August 2018
  • Includes 6-lane bridge across Cottonwood Creek
Stacy Road

Stacy Road


(Greenville Ave to FM 1378)
Project Contact: Joseph Cotton

Completion: Spring 2018
  • TxDOT project
dart

DART Rail Service 



The City of Allen continues to investigate moving rail transit further north in the US 75 corridor. Learn more about DART in Allen.
Ridgemont Drive
(Greenville to US 75) 
Project Contact: Lindy Higginbotham

Completion: December 2017
Ridgemont Drive
(Greenville to US 75) 
Project Contact: Lindy Higginbotham

Completion: December 2017
Ridgemont Drive
(Greenville to US 75) 
Project Contact: Lindy Higginbotham

Completion: December 2017
Ridgemont Drive
(Greenville to US 75) 
Project Contact: Lindy Higginbotham

Completion: December 2017